Tag Archives: reactor

‘New’ reactor types are all nuclear pie in the sky Updated for 2026





Some nuclear enthusiasts and lobbyists favour non-existent Integral Fast Reactors, others favour non-existent Liquid Fluoride Thorium Reactors, others favour non-existent Pebble Bed Modular Reactors, others favour non-existent fusion reactors. And on it goes.

Two to three decades ago, the nuclear industry promised a new generation of gee-whiz ‘Generation IV’ reactors in two to three decades. That’s what they’re still saying now, and that’s what they’ll be saying two to three decades from now. The Generation IV International Forum website states:

“It will take at least two or three decades before the deployment of commercial Gen IV systems. In the meantime, a number of prototypes will need to be built and operated. The Gen IV concepts currently under investigation are not all on the same timeline and some might not even reach the stage of commercial exploitation.”

The World Nuclear Association notes that “progress is seen as slow, and several potential designs have been undergoing evaluation on paper for many years.”

Integral Fast Reactors … it gets ugly moving from blueprint to backyard

Integral Fast Reactors (IFRs) are a case in point. According to the lobbyists they are ready to roll, will be cheap to build and operate, couldn’t be used to feed WMD proliferation, etc. The US and UK governments have been analysing the potential of IFRs.

The UK government found that:

  • the facilities have not been industrially demonstrated;
  • waste disposal issues remain unresolved and could be further complicated if it is deemed necessary to remove sodium from spent fuel to facilitate disposal; and
  • little could be ascertained about cost since General Electric Hitachi refuses to release estimates of capital and operating costs, saying they are “commercially sensitive”.

The US government has also considered the use of IFRs (which it calls Advanced Disposition Reactors – ADR) to manage US plutonium stockpiles and concluded that:

  • the ADR approach would be more than twice as expensive as all the other options under consideration;
  • it would take 18 years to construct an ADR and associated facilities; and
  • the ADR option is associated with “significant technical risk”.

Unsurprisingly, the IFR rhetoric doesn’t match the sober assessments of the UK and US governments. As nuclear engineer Dave Lochbaum from the Union of Concerned
Scientists puts it:

“The IFR looks good on paper. So good, in fact, that we should leave it on paper. For it only gets ugly in moving from blueprint to backyard.”

Small Modular Reactors … no-one actually wants to buy one

In any case, IFRs are yesterday’s news. Now it’s all about Small Modular Reactors (SMRs). The Energy Green Paper recently released by the Australian government is typical of the small-is-beautiful rhetoric:

“The main development in technology since 2006 has been further work on Small Modular Reactors (SMRs). SMRs have the potential to be flexibly deployed, as they are a simpler ‘plug-in’ technology that does not require the same level of operating skills and access to water as traditional, large reactors.”

The rhetoric doesn’t match reality. Interest in SMRs is on the wane. Thus Thomas W. Overton, associate editor of POWER magazine, wrote in a recent article:

“At the graveyard wherein resides the “nuclear renaissance” of the 2000s, a new occupant appears to be moving in: the small modular reactor (SMR). … Over the past year, the SMR industry has been bumping up against an uncomfortable and not-entirely-unpredictable problem: It appears that no one actually wants to buy one.”

Overton notes that in 2013, MidAmerican Energy scuttled plans to build an SMR-based plant in Iowa. This year, Babcock & Wilcox scaled back much of its SMR program and sacked 100 workers in its SMR division. Westinghouse has abandoned its SMR program. As he explains:

“The problem has really been lurking in the idea behind SMRs all along. The reason conventional nuclear plants are built so large is the economies of scale: Big plants can produce power less expensively per kilowatt-hour than smaller ones.

“The SMR concept disdains those economies of scale in favor of others: large-scale standardized manufacturing that will churn out dozens, if not hundreds, of identical plants, each of which would ultimately produce cheaper kilowatt-hours than large one-off designs.

“It’s an attractive idea. But it’s also one that depends on someone building that massive supply chain, since none of it currently exists. … That money would presumably come from customer orders – if there were any. Unfortunately, the SMR “market” doesn’t exist in a vacuum.

“SMRs must compete with cheap natural gas, renewables that continue to decline in cost, and storage options that are rapidly becoming competitive. Worse, those options are available for delivery now, not at the end of a long, uncertain process that still lacks [US Nuclear Regulatory Commission] approval.”

Can’t find customers, can’t find investors

Dr Mark Cooper, Senior Fellow for Economic Analysis at the Institute for Energy and the Environment, Vermont Law School, notes that two US corporations are pulling out of SMR development because they cannot find customers (Westinghouse) or major investors (Babcock and Wilcox). Cooper points to some economic constraints:

“SMR technology will suffer disproportionately from material cost increases because they use more material per MW of capacity. Higher costs will result from: lost economies of scale; higher operating costs; and higher decommissioning costs. Cost estimates that assume quick design approval and deployment are certain to prove to be wildly optimistic.”

Academics M.V. Ramana and Zia Mian state in their detailed analysis of SMRs: “Proponents of the development and large scale deployment of small modular reactors suggest that this approach to nuclear power technology and fuel cycles can resolve the four key problems facing nuclear power today: costs, safety, waste, and proliferation.

“Nuclear developers and vendors seek to encode as many if not all of these priorities into the designs of their specific nuclear reactor. The technical reality, however, is that each of these priorities can drive the requirements on the reactor design in different, sometimes opposing, directions.

“Of the different major SMR designs under development, it seems none meets all four of these challenges simultaneously. In most, if not all designs, it is likely that addressing one of the four problems will involve choices that make one or more of the other problems worse.”

The future is in … decommissioning

Likewise, Kennette Benedict, Executive Director of the Bulletin of the Atomic Scientists, states: “Without a clear-cut case for their advantages, it seems that small nuclear modular reactors are a solution looking for a problem.

“Of course in the world of digital innovation, this kind of upside-down relationship between solution and problem is pretty normal. Smart phones, Twitter, and high-definition television all began as solutions looking for problems.

“In the realm of nuclear technology, however, the enormous expense required to launch a new model as well as the built-in dangers of nuclear fission require a more straightforward relationship between problem and solution.

“Small modular nuclear reactors may be attractive, but they will not, in themselves, offer satisfactory solutions to the most pressing problems of nuclear energy: high cost, safety, and weapons proliferation.”

And as Westinghouse CEO Danny Roderick said in January: “The problem I have with SMRs is not the technology, it’s not the deployment – it’s that there’s no customers.”

Instead of going for SMRs, IFRs, Pebble Bed Reactors or thorium technologies, Westinghouse is looking to triple the one area where it really does have customers: its decommissioning business. “We see this as a $1 billion-per-year business for us”, Roderick said.

With the world’s fleet of mostly middle-aged reactors inexorably becoming a fleet of mostly ageing, decrepit reactors, Westinghouse is getting ahead of the game.

The writing is on the wall

Some SMR R&D work continues but it all seems to be leading to the conclusions mentioned above. Argentina is ahead of the rest, with construction underway on a 27 MWe reactor – but the cost equates to an astronomical US$15.2 billion per 1,000 MWe. Argentina’s expertise with reactor technology stems from its covert weapons program from the 1960s to the early 1980s.

So work continues on SMRs but the writing’s on the wall and it’s time for the nuclear lobby to come up with another gee-whiz next-gen fail-safe reactor type to promote … perhaps a giant fusion reactor located out of harm’s way, 150 million kilometres from Earth.

And while the ‘small is beautiful’ approach is faltering, so too is the ‘bigger is better’ mantra. The 1,600 MW Olkiluoto-3 European Pressurized Reactor (EPR) under construction in Finland is nine years behind schedule (and counting) and US$6.9 billion over-budget (and counting).

The UK is embarking on a hotly-contested plan to build two 1,600 MW EPRs at Hinkley Point with a capital cost of US$26 billion and mind-boggling public subsidies.

Economic consulting firm Liberum Capital said Hinkley Point will be “both the most expensive power station in the world and also the plant with the longest construction period.”

 


 

Dr Jim Green is the national nuclear campaigner with Friends of the Earth Australia and editor of the Nuclear Monitor newsletter. Nuclear Monitor is published 20 times a year. It has been publishing deeply researched, often strongly critical articles on all aspects of the nuclear cycle since 1978. A must-read for all those who work on this issue!

 

 




384864

‘New’ reactor types are all nuclear pie in the sky Updated for 2026





Some nuclear enthusiasts and lobbyists favour non-existent Integral Fast Reactors, others favour non-existent Liquid Fluoride Thorium Reactors, others favour non-existent Pebble Bed Modular Reactors, others favour non-existent fusion reactors. And on it goes.

Two to three decades ago, the nuclear industry promised a new generation of gee-whiz ‘Generation IV’ reactors in two to three decades. That’s what they’re still saying now, and that’s what they’ll be saying two to three decades from now. The Generation IV International Forum website states:

“It will take at least two or three decades before the deployment of commercial Gen IV systems. In the meantime, a number of prototypes will need to be built and operated. The Gen IV concepts currently under investigation are not all on the same timeline and some might not even reach the stage of commercial exploitation.”

The World Nuclear Association notes that “progress is seen as slow, and several potential designs have been undergoing evaluation on paper for many years.”

Integral Fast Reactors … it gets ugly moving from blueprint to backyard

Integral Fast Reactors (IFRs) are a case in point. According to the lobbyists they are ready to roll, will be cheap to build and operate, couldn’t be used to feed WMD proliferation, etc. The US and UK governments have been analysing the potential of IFRs.

The UK government found that:

  • the facilities have not been industrially demonstrated;
  • waste disposal issues remain unresolved and could be further complicated if it is deemed necessary to remove sodium from spent fuel to facilitate disposal; and
  • little could be ascertained about cost since General Electric Hitachi refuses to release estimates of capital and operating costs, saying they are “commercially sensitive”.

The US government has also considered the use of IFRs (which it calls Advanced Disposition Reactors – ADR) to manage US plutonium stockpiles and concluded that:

  • the ADR approach would be more than twice as expensive as all the other options under consideration;
  • it would take 18 years to construct an ADR and associated facilities; and
  • the ADR option is associated with “significant technical risk”.

Unsurprisingly, the IFR rhetoric doesn’t match the sobre assessments of the UK and US governments. As nuclear engineer Dave Lochbaum from the Union of Concerned
Scientists puts it:

“The IFR looks good on paper. So good, in fact, that we should leave it on paper. For it only gets ugly in moving from blueprint to backyard.”

Small Modular Reactors … no-one actually wants to buy one

In any case, IFRs are yesterday’s news. Now it’s all about Small Modular Reactors (SMRs). The Energy Green Paper recently released by the Australian government is typical of the small-is-beautiful rhetoric:

“The main development in technology since 2006 has been further work on Small Modular Reactors (SMRs). SMRs have the potential to be flexibly deployed, as they are a simpler ‘plug-in’ technology that does not require the same level of operating skills and access to water as traditional, large reactors.”

The rhetoric doesn’t match reality. Interest in SMRs is on the wane. Thus Thomas W. Overton, associate editor of POWER magazine, wrote in a recent article:

“At the graveyard wherein resides the “nuclear renaissance” of the 2000s, a new occupant appears to be moving in: the small modular reactor (SMR). … Over the past year, the SMR industry has been bumping up against an uncomfortable and not-entirely-unpredictable problem: It appears that no one actually wants to buy one.”

Overton notes that in 2013, MidAmerican Energy scuttled plans to build an SMR-based plant in Iowa. This year, Babcock & Wilcox scaled back much of its SMR program and sacked 100 workers in its SMR division. Westinghouse has abandoned its SMR program. As he explains:

“The problem has really been lurking in the idea behind SMRs all along. The reason conventional nuclear plants are built so large is the economies of scale: Big plants can produce power less expensively per kilowatt-hour than smaller ones.

“The SMR concept disdains those economies of scale in favor of others: large-scale standardized manufacturing that will churn out dozens, if not hundreds, of identical plants, each of which would ultimately produce cheaper kilowatt-hours than large one-off designs.

“It’s an attractive idea. But it’s also one that depends on someone building that massive supply chain, since none of it currently exists. … That money would presumably come from customer orders – if there were any. Unfortunately, the SMR “market” doesn’t exist in a vacuum.

“SMRs must compete with cheap natural gas, renewables that continue to decline in cost, and storage options that are rapidly becoming competitive. Worse, those options are available for delivery now, not at the end of a long, uncertain process that still lacks [US Nuclear Regulatory Commission] approval.”

Can’t find customers, can’t find investors

Dr Mark Cooper, Senior Fellow for Economic Analysis at the Institute for Energy and the Environment, Vermont Law School, notes that two US corporations are pulling out of SMR development because they cannot find customers (Westinghouse) or major investors (Babcock and Wilcox). Cooper points to some economic constraints:

“SMR technology will suffer disproportionately from material cost increases because they use more material per MW of capacity. Higher costs will result from: lost economies of scale; higher operating costs; and higher decommissioning costs. Cost estimates that assume quick design approval and deployment are certain to prove to be wildly optimistic.”

Academics M.V. Ramana and Zia Mian state in their detailed analysis of SMRs: “Proponents of the development and large scale deployment of small modular reactors suggest that this approach to nuclear power technology and fuel cycles can resolve the four key problems facing nuclear power today: costs, safety, waste, and proliferation.

“Nuclear developers and vendors seek to encode as many if not all of these priorities into the designs of their specific nuclear reactor. The technical reality, however, is that each of these priorities can drive the requirements on the reactor design in different, sometimes opposing, directions.

“Of the different major SMR designs under development, it seems none meets all four of these challenges simultaneously. In most, if not all designs, it is likely that addressing one of the four problems will involve choices that make one or more of the other problems worse.”

The future is in … decommissioning

Likewise, Kennette Benedict, Executive Director of the Bulletin of the Atomic Scientists, states: “Without a clear-cut case for their advantages, it seems that small nuclear modular reactors are a solution looking for a problem.

“Of course in the world of digital innovation, this kind of upside-down relationship between solution and problem is pretty normal. Smart phones, Twitter, and high-definition television all began as solutions looking for problems.

“In the realm of nuclear technology, however, the enormous expense required to launch a new model as well as the built-in dangers of nuclear fission require a more straightforward relationship between problem and solution.

“Small modular nuclear reactors may be attractive, but they will not, in themselves, offer satisfactory solutions to the most pressing problems of nuclear energy: high cost, safety, and weapons proliferation.”

And as Westinghouse CEO Danny Roderick said in January: “The problem I have with SMRs is not the technology, it’s not the deployment – it’s that there’s no customers.”

Instead of going for SMRs, IFRs, Pebble Bed Reactors or thorium technologies, Westinghouse is looking to triple the one area where it really does have customers: its decommissioning business. “We see this as a $1 billion-per-year business for us”, Roderick said.

With the world’s fleet of mostly middle-aged reactors inexorably becoming a fleet of mostly ageing, decrepit reactors, Westinghouse is getting ahead of the game.

The writing is on the wall

Some SMR R&D work continues but it all seems to be leading to the conclusions mentioned above. Argentina is ahead of the rest, with construction underway on a 27 MWe reactor – but the cost equates to an astronomical US$15.2 billion per 1,000 MWe. Argentina’s expertise with reactor technology stems from its covert weapons program from the 1960s to the early 1980s.

So work continues on SMRs but the writing’s on the wall and it’s time for the nuclear lobby to come up with another gee-whiz next-gen fail-safe reactor type to promote … perhaps a giant fusion reactor located out of harm’s way, 150 million kilometres from Earth.

And while the ‘small is beautiful’ approach is faltering, so too is the ‘bigger is better’ mantra. The 1,600 MW Olkiluoto-3 European Pressurized Reactor (EPR) under construction in Finland is nine years behind schedule (and counting) and US$6.9 billion over-budget (and counting).

The UK is embarking on a hotly-contested plan to build two 1,600 MW EPRs at Hinkley Point with a capital cost of US$26 billion and mind-boggling public subsidies.

Economic consulting firm Liberum Capital said Hinkley Point will be “both the most expensive power station in the world and also the plant with the longest construction period.”

 


 

Dr Jim Green is the national nuclear campaigner with Friends of the Earth Australia and editor of the Nuclear Monitor newsletter. Nuclear Monitor is published 20 times a year. It has been publishing deeply researched, often strongly critical articles on all aspects of the nuclear cycle since 1978. A must-read for all those who work on this issue!

 

 




384864

Three in every four nuclear power builds worldwide are running late Updated for 2026





As of this month, 49 of 66 reactors under construction around the world are running behind schedule, according to an updated analysis conducted by the authors of the World Nuclear Industry Status Report 2014.

The study takes into account several delay announcements in recent weeks:

  • USA: two reactors, Virgil C. Summer Nuclear Station Unit 2 and Virgil C. Summer Nuclear Station Unit 3;
  • South Korea: two reactors – Shin-Hanul-2 and Shin-Wolsong-2;
  • and Finland: Olkiluoto-3.

Little is known about the progress on four nuclear reactors in India. All the other reactor projects have been under way for less than two years, which makes it difficult to identify delays in the absence of full access to information.

The full and up to date list of reactors under construction and related delay details is available at World Reactor Delays.

The European Pressurised Reactor (EPR)

The study highlights the two EPR-design reactors currently under construction: Finland’s Olkiluoto-3 and France’s Flamanville-3. Both are running about $7 billion over their initial budgets and now projected to cost more than $11 billion.

EDF’s Flamanville reactor was due to be completed by 2012 at a cost of €3.3 billion, but is now projected for completion in 2016 at a cost of €8.5 billion.

Finland’s Olkiluoto-3 reactor, the first EPR construction project, is likely to be a decade behind schedule upon delivery, with a projected completion date of 2018. Construction of the 1.6GW plant began in 2005 and was originally due for completion in 2009. Cost figures are similar to those for Flamanville.

Despite the severe problems with existing EPR projects, the French parastatal power company EDF is planning to build a twin-reactor 3.2GW plant in the UK at Hinkley C in Somerset.

The UK Government strongly supports the project and has agreed terms for a support package that may be worth as much as £100 billion over its lifetime. It includes both a guaranteed electricity price double current wholesale market levels (at £92.50 per megawatt hour) and a £10 billion construction finance guarantee.

Critics like Nikki Clark of the Stop Hinkley campaign group have denounced the UK’s choice of the EPR design as “insane” given the delays and cost overruns in France and Finland.

The support package for Hinkley C is under review by the European Commission as possible ‘illegal state aid’ and may never win approval. The reactors are not included in the study since construction has not proceeded beyond extensive groundworks.

Delays a key factor behind rising costs

Mycle Schneider, Paris-based international consultant on energy and nuclear policy and lead author of ‘The World Nuclear Industry Status Report 2014′ said:

“Delays in construction – some of them multi-year – are a key factor behind rising costs and the clear trend of the shrinking share of nuclear energy in the world’s power production, which declined steadily from a historic peak of 17.6% in 1996 to 10.8% in 2013.

“That trend is likely to persist as costly construction delays continue to dog the relatively small number of new reactor projects around the globe.”

Contrary to what is often claimed in the United States by proponents of nuclear power, he added, “the reality is that other nations around the globe do not have a better track record when it comes to delivering nuclear reactor projects on time and on budget.”

The global picture

According to the study:

  • China – often cited in the US as an example of where nuclear power is being delivered on time and inexpensively – is actually experiencing construction delays at 20 of its 27 reactor projects.
  • Russia is seeing delays at nine out of nine reactor projects.
  • India is reporting delays at two out of six reactor projects, but little information is available about the on-time status of the other four.
  • South Korea is seeing delays at four out of five reactor projects.
  • The United States is reporting delays at all five new reactor projects now under construction.
  • Ukraine’s two reactors were commenced in 1986-1987, and grid connection is officially due in 2015-2016.
  • Five reactors in Pakistan (2), Slovakia (2) and Brazil (1) are also running behind schedule.
  • Finland – Olkiluoto EPR delayed by almost a decade (see above).
  • France – Flamanvile EPR four years behind schedule (see above).

Of these eight reactors have been listed as ‘under construction’ for more than 20 years, and another for 12 years.

With Belarus, a new country was added in the last year to the list of nations engaged in nuclear projects, while Taiwan has halted construction work at two units. Fourteen countries are currently building nuclear power plants.

The remaining 13 reactors all started construction in 2012 and after, making it hard to see how construction is advancing. They are also in countries with little open information on building progress.These 13 reactors comprise: Argentina (1), Belarus (2), China (7), South Korea (1), UAE (2).

“This is by no means any guarantee that these plants are factually on time, let alone on budget”, says Schneider.

Contruction delays – a feature of nuclear power for 40 years

“For the last 40 years, the US nuclear power industry has been plagued by construction delays and by cost overruns”, comments Peter Bradford, adjunct professor on Nuclear Power and Public Policy, Vermont Law School.

The former member of the US Nuclear Regulatory Commission, and former chair of the New York and Maine state utility regulatory commissions, continued:

“Because nuclear power is already more expensive than alternative ways both of generating electricity and of fighting climate change, these delays and overruns further undermine nuclear power’s claim that special nuclear subsidies are an essential part of the world’s climate change strategy.”

 


 

Further information: http://bit.ly/worldreactordelays.

 

 