Tag Archives: launch

KAIST and Hanwha Solutions Launch Eco-Friendly Bio-Platform to Replace Petroleum-Derived Naphtha

Introduction to the Eco-Friendly Bio-Platform

In a groundbreaking initiative, KAIST (Korea Advanced Institute of Science and Technology) has partnered with Hanwha Solutions to establish an eco-friendly bio-platform aimed at replacing petroleum-derived naphtha. This collaboration signifies a significant step forward in the quest for sustainable alternatives in the chemical industry, addressing the urgent need for environmentally friendly solutions amidst growing concerns over climate change and fossil fuel dependency.

Understanding Naphtha and Its Environmental Impact

Naphtha, a liquid hydrocarbon mixture, is primarily derived from crude oil and is extensively used as a feedstock in the production of various chemicals, including plastics, fertilizers, and synthetic fibers. The reliance on petroleum-based naphtha not only contributes to greenhouse gas emissions but also poses risks related to oil spills and resource depletion.

As global awareness of these issues increases, the search for renewable and biodegradable alternatives has become imperative. This is where KAIST and Hanwha Solutions’ innovative bio-platform comes into play, potentially revolutionizing the chemical manufacturing landscape.

The Bio-Platform: A Closer Look

The newly established eco-friendly bio-platform aims to utilize biomass as a primary feedstock to produce sustainable alternatives to petroleum-based naphtha. By focusing on biomass, the initiative promotes the circular economy, which emphasizes resource efficiency, waste reduction, and environmental protection.

Biomass Utilization

Biomass is organic material derived from plants and animals, which can be converted into biofuels, bioplastics, and other bio-based chemicals. The KAIST-Hanwha Solutions collaboration is set to explore various biomass sources, including agricultural waste, forestry residues, and algae, to develop a sustainable production process.

Innovative Production Techniques

This initiative is not just about substituting one material for another; it involves rethinking the entire production process. Advanced biotechnological methods, such as fermentation and enzymatic conversion, will be harnessed to transform biomass into valuable chemicals. These innovative techniques can lead to a reduction in energy consumption and lower emissions compared to traditional methods.

Benefits of the Eco-Friendly Bio-Platform

The establishment of this bio-platform presents numerous benefits, both environmentally and economically. Here are some key advantages:

1. Reduction in Carbon Footprint

By replacing petroleum-derived naphtha with bio-based alternatives, the initiative aims to significantly reduce carbon dioxide emissions throughout the production lifecycle. This shift could play a crucial role in combating climate change and promoting sustainability.

2. Resource Diversification

Utilizing biomass as a feedstock diversifies the resources available for chemical production, reducing dependence on fossil fuels. This transition can enhance energy security and stabilize supply chains, particularly in regions vulnerable to oil price fluctuations.

3. Economic Opportunities

The development of a bio-platform can create new job opportunities in the green economy. From biomass collection and processing to advanced research and development roles, the initiative has the potential to stimulate local economies and foster innovation.

4. Enhanced Public Health

By producing cleaner alternatives to petroleum-derived chemicals, the bio-platform can contribute to improved air and water quality. Reducing the reliance on toxic petrochemicals can also have positive implications for public health, minimizing exposure to harmful substances.

Challenges and Considerations

While the KAIST-Hanwha Solutions bio-platform presents exciting possibilities, it is essential to acknowledge the challenges that lie ahead. Transitioning from established petroleum-based systems to new bio-based processes will require significant investment, research, and development. Additionally, scalability remains a critical concern; ensuring that these sustainable alternatives can be produced at a competitive cost and volume is paramount.

Regulatory and Market Dynamics

The success of the eco-friendly bio-platform will also depend on supportive regulatory frameworks and market acceptance. Policymakers need to incentivize the shift towards bio-based chemicals through subsidies, tax breaks, and other measures. Furthermore, consumer awareness and demand for sustainable products will play a vital role in driving the adoption of these new materials.

The Future of Sustainable Chemicals

The establishment of the KAIST-Hanwha Solutions eco-friendly bio-platform represents a pivotal moment in the move towards sustainable chemical production. As the world grapples with the challenges posed by climate change and resource depletion, initiatives like this offer a glimpse of a greener future.

By harnessing the potential of biomass and innovative production techniques, this collaboration could pave the way for a new era in the chemical industry—one that prioritizes environmental stewardship, economic resilience, and public health.

Conclusion

In conclusion, the partnership between KAIST and Hanwha Solutions to create an eco-friendly bio-platform is a commendable step toward replacing petroleum-derived naphtha with sustainable alternatives. As they navigate the challenges ahead, their progress will not only benefit the chemical industry but also contribute to a more sustainable and eco-conscious world.

Frequently Asked Questions (FAQ)

What exactly does KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​ mean?

In practical terms, it mainly concerns KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​  EurekAlert!. Understanding this aspect is the first step to mastering KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​.

What is the real impact of KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​ today?

The greatest impact is observed when we consider that dynamics are changing rapidly. This explains much of the current interest.

How does KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​ work in practice?

A key element to consider is that a methodical approach makes the difference. Many experts agree on this point when analyzing KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​.

What are the benefits related to KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​?

To study it properly, it is essential to start from real data and observe how trends are evolving in the reference market of KAIST-Hanwha Solutions Establishes ‘Eco-Friendly Bio-Platform’ to Replace Petroleum-Derived Naphtha​.

Greenpeace Energy to launch legal challenge to UK nuclear subsidies Updated for 2026





German green power supply company Greenpeace Energy (GPE) will take legal action against the European Commission because it has approved State aid worth billions for the building of the UK’s new Hinkley Point C nuclear plant.

According to GPE, the nuclear subsidy “threatens to distort competition in the European Union against genuine clean energy” and “could act as precedent and further undermine the EU energy market.”

“Highly subsidised nuclear power from this plant will noticeably distort European competitiveness. It will have an effect on prices at the power exchange in Germany as well”, says Sönke Tangermann, GPE’s managing director.

“This effect will have economic disadvantages for committed green power providers like us, and that’s why we are going to court.”

He adds that GPE will file a plea for annulment at the European Court of Justice in Luxembourg “as soon as the Commission’s State aid approval is published in the EU’s Official Journal and the period prescribed for bringing an action begins.”

Austria is also expected to launch a legal action against the Hinkley C subsidies – in the face of menacing threats from UK diplomats that the UK would “embrace any future opportunity that arises to sue or damage Austria in areas which have strong domestic political implications.”

Far higher subsidies to nuclear than to renewables

Last October the EU Commission approved State aid for the new build of two nuclear reactors at Hinkley Point in Somerset. GPE estimates that the immediate subsidy is worth about €22 billion, or £16 billion.

However the picture is complex as the aid package includes an inflation-proof generation subsidy of £92.50 per MWh for 35 years, construction guarantees, limits on liability for decommissioning, and a low accident liabilty cut-off. Other analysts believe the true cost as far higher and could amount to £30 billion or more.

The generation subsidy alone guarantees Hinkley’s power a wholesale price of £92.50 per MHh, double the market price, or 9.25p per unit – equivalent to almost 13€c. Adding all the elements together, says GPE, “The resulting subsidy is far higher than that for wind or solar power in Germany.”

It’s also much higher than renewable energy subsidies in the UK. Last week the UK government awarded contracts to renewable energy generators under its new ‘contracts for difference’ (CFD) auction. Typically wind generators were bidding £82.50 per MHh, and solar generators came in even lower, at £79.23 per MWh and £50 per MWh.

Also the contracts are for only 15 years – as opposed to the 35 years for Hinkley C – and contain no additional support or guarantees. The entire CFD package for new renewable energy capacity is limited to just £50 million per year, rising to £65 million in future years.

As reported on The Ecologist, the effect of the UK’s energy policy will be to almost kill off the flourishing solar sector, reducing the rate of new solar build from 2,000-3,000 MWh per year, to an estimated 32MW.

Many critics believe that the government is cutting back on renewables that are increasingly competitive against fossil fuels as prices rapidly drop, to make way for far higher-priced nuclear power.

Hinkley threatens to distort the entire European market

An expert opinion commissioned by Greenpeace Energy from analysts Energy Brainpool shows that Hinkley Point C will lead to a shift in price levels in the European electricity market.

The opinion explains that lower prices for electricity at the power exchange in Germany will discriminate against those suppliers that procure green power at fixed prices directly from plant operators in the framework of the German Renewable Energies Act.

“Unlike the claims of Prime Minister Cameron, a new reactor built at Hinkley Point, supported by billions of taxpayers money, is not a purely British affair, but directly disadvantages us as a German enterprise active in the European electricity market”, says Tangermann.

Due to the price effects of Hinkley Point C, the costs of the system laid out in Germany’s Renewable Energies Act (EEG) to foster renewables are likely to rise because the operators of renewable energy plants – with fixed feed-in tariffs – would in future have to be paid a larger difference in the electricity price at the power exchange.

This would probably cause a small increase in the renewable energy surcharge, while “the strain it would put on the EEG system is an outrage”, says Tangermann.

Will Hinkley corner European Investment Funds?

GPE’s other fear is that Hinkley, and other nuclear projects elsewhere in Europe, could grab a huge share of the European Investment Fund presented by Jean-Claude Juncker, president of the EU Commission, when it enters into force.

The UK has already applied for €46 billion to fund Hinkley C and two other nuclear power stations from the projected €315 billion fund, and this could be essential as other potential funders have withdrawn. Poland is also applying for €12 billion for new nuclear build.

Moreover, the EU intends to massively extend cross-border power lines, meaning the negative effect of this development, as calculated by Energy Brainpool, would be reinforced on a massive scale.As such GPE sees in the approval of State aid for Hinkley Point C a precedent for other nuclear projects that will hugely distort Europe’s energy market, says Tangemann:

“If the Commission’s approval goes unchallenged, then Hinkley Point C is just the tip of the iceberg, which is why we are calling on the German government to take legal action against the unfair State aid approval for Hinkley Point C. It must not open the door to other hazardous and absurdly expensive nuclear power projects in Europe.”

Germany’s biggest independent energy co-op

GPE is Germany’s largest national, independent energy cooperative, supplying clean power to more than 111,000 customers, of which about 9,000 are businesses. It is organised as a cooperative with 23,000 members whose contributions provide a solid equity capital base.

Through its subsidiary Planet Energy it also builds its own power plants, and has 11 wind farms (see photo) and three photovoltaic plants totalling 65MW are already in operation.

GPE has appointed Dr. Dörte Fouquet at the Becker Büttner Held law office, specialists in this area, to prepare the application for the plea for annulment and assist in subsequent proceedings.

In coming weeks, Greenpeace Energy will also review the possibility of joining forces with other stakeholders in Germany’s energy market for bringing legal action as a collective.

 


 

Principal source: Greenpeace Energy.

Oliver Tickell edits The Ecologist.

 




390968

Austria: ‘we will launch Hinkley C nuclear subsidy legal challenge by April’ Updated for 2026





Austria is to launch a legal challenge against the European Union’s (EU) decision to allow billions of pounds of subsidies for Hinkley Point C, casting fresh doubt over the UK’s first planned nuclear reactors in 20 years.

In October, the EU approved the controversial £17.6bn subsidy deal for the power station, which is expected to provide 7% of the UK’s electricity by 2023.

David Cameron had previously hailed the subsidy deal between the French state-owned EDF and the UK government as “a very big day for our country”. He also described the signing of the Hinkley deal as marking the next generation of nuclear power in Britain, for its ability to meet energy demand and contribute to long-term security of supply.

But the appeal by Austria, a non-nuclear nation, will be launched by April and could delay a final investment decision by the UK government for over two years.

The Guardian understands that Luxembourg is very likely to support the case in the European Court of Justice, arguing that the UK’s loan guarantees – over a 35-year period – constitute illegal state aid. Another EU country may follow suit.

“There has been a high-level decision by our Chancellor and Vice Chancellor to challenge the EU decision on Hinkley within two months of its publication in the EU’s official journal”, said Andreas Molin, the director of Austria’s environment ministry. The journal’s publication is expected in the next fortnight.

Stefan Pehringer, a foreign policy adviser to the Austrian federal chancellory said: “The Austrian government has announced its readiness to appeal against the EC’s [European Commission] decision concerning state aid for the Hinkley Point project, as it does not consider nuclear power to be a sustainable form of technology – neither in environmental nor in economic terms.”

Can Hinkley survive the 2015 election?

Work has already begun at the Hinkley site, which the UK government said will have a capacity of 3.3GW, with the electricity it generates bought at a strike-price of £92.50 per megawatt hour, around double the market rate.

EDF had planned to sign a long-awaited funding agreement with its Chinese investment partners in March, thought to be key to settling procurement plans for the £24.5bn build, and the precursor to a final investment decision.

But the lawsuit may delay such plans, and introduce uncertainty about the UK’s attitude towards Hinkley after elections in May.

The Austrian government’s analysis suggests that European court cases of this nature typically last for one and a half years. But “as this is going to be a more complicated and fundamental case, it will last a little bit longer”, Molin said. “Two years could be a rough guess.”

He added: “If you accept the argument that Hinkley constitutes a ‘market failure’ as put forward by the Commission, you could apply it to all other means of electricity production, probably all other forms of energy conversion, and it might even apply beyond the energy sector. We think that the single energy market itself is at stake in this case.”

The Commission’s hurried and paradoxical decision

The EU’s original decision last year surprised many observers, as the then-competition commissioner Joaquín Almunia had previously expressed scepticism about Hinkley’s’ conformity with an exhaustive list of strict state aid criteria.

These govern proportionality, decarbonisation, the potential for market distortion, the definition of ‘market failures’ and, crucially, whether the public monies advance an “objective of common interest” for the bloc.

No grounds for the Commission’s volte-face have yet been published, but the Guardian has seen a draft of the EU decision from last October, suggesting that one key decider had been advised that Hinkley advanced an EU ‘common interest’ around security of supply.

A Commission investigation declared itself “unsure” whether the reactor would resolve the UK’s security of supply issues, and was unconvinced that ‘diversification’ of supplies, on its own, would justify the monies involved.

“The Commission however accepted that the decision was in line with the Euratom treaty”, the draft ruling says. The Euratom treaty obliges member states to facilitate investments in nuclear power and encourage ventures that lead to the technology’s development.

Molin said that Austria would argue that the Euratom treaty could not be used in this way in state aid cases, but there would be other lines of dispute. “We will try to prove that the commission did not consider all the things which it should have considered and that there were some procedural flaws”, he said.

Minutes from the Commission’s internal discussion of the issue show that the EC’s president at the time, José Manuel Barroso, viewed the Hinkley decision as unprecedented, and said that it “touched on a politically sensitive topic”.

No contract for the Hinkley plant was put out to tender, and the ruling sparked outrage among environmentalists in the EU, that shows no signs of dying down.

“The Commission took a political decision disguised as a legal one”, said Mark Johnston, a senior adviser to the European Policy Centre. “Barroso thought it would be easier to bend over for Cameron than to defend the single energy market. The significance of the case for energy investments across Europe could not be greater.”

A ‘fatal blow’, claim the Greens

Molly Scott Cato, the Green Party MEP for the South West region, which includes Hinkley, said: “I think that this court case is certainly going to delay the signing and also the construction of Hinkley.”

“As one of the government’s main arguments for Hinkley was that it would solve the ‘energy gap’ before renewables could be brought onstream, it is a fatal blow to Hinkley as part of a future energy strategy for the UK.”

Natalie Bennett, the leader of the Green Party, said that such claims now seemed risible. “I think we have seen the final generation of nuclear power, I am very pleased to say. It’s gone, it’s dusted. Lets focus on evidence-based renewables and energy conservation futures.”

But the UKIP MEP and energy spokesman, Roger Helmer, offered strong support for nuclear energy, qualified only by a caveat that the government’s Hinkley deal had been “excessively expensive” because of regulatory uncertainty from Brussels.

“Given that Hinkley is a trailblazer for the new generation of nuclear and now looks like being held up for a long period of time, it will be extremely damaging – not just for nuclear but across the whole spectrum of industry”, he said.

No grounds for such state aid in EU treaties

Dr Dörte Fouquet, a lawyer for the Brussels-based law firm Becker Büttner Held, which specialises in energy and competition law, said Austria’s chances of success were “pretty high” because there were no grounds for giving such state aid under EU treaty law and Austria would question the common European interest in building a nuclear power plant in the UK.

She added that long delays now appeared inevitable: “A court process that kicks off in May would take a minimum of two years and if it goes into appeals, you’d then be looking at another two years. So it could be a minimum of three and a maximum of four years or longer.

But the Department of Energy and Climate Change remained bullish. “The UK is confident that the state aid case for Hinkley Point C is legally robust and we vigorously support the European Commission’s defence of its decision last year”, a  spokesman told the Guardian.

“This brings us one step closer to seeing new nuclear as part of our future low carbon energy mix. We have no reason to believe that Austria, or any other party, is preparing a case which has any merit.”

But DECC did not respond to questions about the effect that a lengthy court case might have on cost over-runs or a final investment decision.

The renewables industry has bridled at what some see as double-standards in EU decisions last year denying state aid to renewable energy in Germany, while allowing it for nuclear in the UK.

“It’s puzzling why the European Commission has decided to have a set of rules for one energy source and entirely different set for another”, said European Wind Energy Association spokesman Oliver Joy.

“If we want a level playing field for all energy forms in the EU then we need common standards that allow all technologies to compete on an equal footing.”

 


 

Arthur Neslen is the Europe environment correspondent at the Guardian. He has previously worked for the BBC, the Economist, Al Jazeera, and EurActiv, where his journalism won environmental awards. He has written two books about Israeli and Palestinian identity.

This article is a synthesis of two articles by Arthur Nelsen originally published on the Guardian: ‘Austria to launch lawsuit over Hinkley Point C nuclear subsidies‘ and ‘UK nuclear ambitions dealt fatal blow by Austrian legal challenge, say Greens‘. It is published on The Ecologist by kind permission via the Guardian Environment Network.

 

 




389354

Austria: ‘we will launch Hinkley C nuclear subsidy legal challenge by April’ Updated for 2026





Austria is to launch a legal challenge against the European Union’s (EU) decision to allow billions of pounds of subsidies for Hinkley Point C, casting fresh doubt over the UK’s first planned nuclear reactors in 20 years.

In October, the EU approved the controversial £17.6bn subsidy deal for the power station, which is expected to provide 7% of the UK’s electricity by 2023.

David Cameron had previously hailed the subsidy deal between the French state-owned EDF and the UK government as “a very big day for our country”. He also described the signing of the Hinkley deal as marking the next generation of nuclear power in Britain, for its ability to meet energy demand and contribute to long-term security of supply.

But the appeal by Austria, a non-nuclear nation, will be launched by April and could delay a final investment decision by the UK government for over two years.

The Guardian understands that Luxembourg is very likely to support the case in the European Court of Justice, arguing that the UK’s loan guarantees – over a 35-year period – constitute illegal state aid. Another EU country may follow suit.

“There has been a high-level decision by our Chancellor and Vice Chancellor to challenge the EU decision on Hinkley within two months of its publication in the EU’s official journal”, said Andreas Molin, the director of Austria’s environment ministry. The journal’s publication is expected in the next fortnight.

Stefan Pehringer, a foreign policy adviser to the Austrian federal chancellory said: “The Austrian government has announced its readiness to appeal against the EC’s [European Commission] decision concerning state aid for the Hinkley Point project, as it does not consider nuclear power to be a sustainable form of technology – neither in environmental nor in economic terms.”

Can Hinkley survive the 2015 election?

Work has already begun at the Hinkley site, which the UK government said will have a capacity of 3.3GW, with the electricity it generates bought at a strike-price of £92.50 per megawatt hour, around double the market rate.

EDF had planned to sign a long-awaited funding agreement with its Chinese investment partners in March, thought to be key to settling procurement plans for the £24.5bn build, and the precursor to a final investment decision.

But the lawsuit may delay such plans, and introduce uncertainty about the UK’s attitude towards Hinkley after elections in May.

The Austrian government’s analysis suggests that European court cases of this nature typically last for one and a half years. But “as this is going to be a more complicated and fundamental case, it will last a little bit longer”, Molin said. “Two years could be a rough guess.”

He added: “If you accept the argument that Hinkley constitutes a ‘market failure’ as put forward by the Commission, you could apply it to all other means of electricity production, probably all other forms of energy conversion, and it might even apply beyond the energy sector. We think that the single energy market itself is at stake in this case.”

The Commission’s hurried and paradoxical decision

The EU’s original decision last year surprised many observers, as the then-competition commissioner Joaquín Almunia had previously expressed scepticism about Hinkley’s’ conformity with an exhaustive list of strict state aid criteria.

These govern proportionality, decarbonisation, the potential for market distortion, the definition of ‘market failures’ and, crucially, whether the public monies advance an “objective of common interest” for the bloc.

No grounds for the Commission’s volte-face have yet been published, but the Guardian has seen a draft of the EU decision from last October, suggesting that one key decider had been advised that Hinkley advanced an EU ‘common interest’ around security of supply.

A Commission investigation declared itself “unsure” whether the reactor would resolve the UK’s security of supply issues, and was unconvinced that ‘diversification’ of supplies, on its own, would justify the monies involved.

“The Commission however accepted that the decision was in line with the Euratom treaty”, the draft ruling says. The Euratom treaty obliges member states to facilitate investments in nuclear power and encourage ventures that lead to the technology’s development.

Molin said that Austria would argue that the Euratom treaty could not be used in this way in state aid cases, but there would be other lines of dispute. “We will try to prove that the commission did not consider all the things which it should have considered and that there were some procedural flaws”, he said.

Minutes from the Commission’s internal discussion of the issue show that the EC’s president at the time, José Manuel Barroso, viewed the Hinkley decision as unprecedented, and said that it “touched on a politically sensitive topic”.

No contract for the Hinkley plant was put out to tender, and the ruling sparked outrage among environmentalists in the EU, that shows no signs of dying down.

“The Commission took a political decision disguised as a legal one”, said Mark Johnston, a senior adviser to the European Policy Centre. “Barroso thought it would be easier to bend over for Cameron than to defend the single energy market. The significance of the case for energy investments across Europe could not be greater.”

A ‘fatal blow’, claim the Greens

Molly Scott Cato, the Green Party MEP for the South West region, which includes Hinkley, said: “I think that this court case is certainly going to delay the signing and also the construction of Hinkley.”

“As one of the government’s main arguments for Hinkley was that it would solve the ‘energy gap’ before renewables could be brought onstream, it is a fatal blow to Hinkley as part of a future energy strategy for the UK.”

Natalie Bennett, the leader of the Green Party, said that such claims now seemed risible. “I think we have seen the final generation of nuclear power, I am very pleased to say. It’s gone, it’s dusted. Lets focus on evidence-based renewables and energy conservation futures.”

But the UKIP MEP and energy spokesman, Roger Helmer, offered strong support for nuclear energy, qualified only by a caveat that the government’s Hinkley deal had been “excessively expensive” because of regulatory uncertainty from Brussels.

“Given that Hinkley is a trailblazer for the new generation of nuclear and now looks like being held up for a long period of time, it will be extremely damaging – not just for nuclear but across the whole spectrum of industry”, he said.

No grounds for such state aid in EU treaties

Dr Dörte Fouquet, a lawyer for the Brussels-based law firm Becker Büttner Held, which specialises in energy and competition law, said Austria’s chances of success were “pretty high” because there were no grounds for giving such state aid under EU treaty law and Austria would question the common European interest in building a nuclear power plant in the UK.

She added that long delays now appeared inevitable: “A court process that kicks off in May would take a minimum of two years and if it goes into appeals, you’d then be looking at another two years. So it could be a minimum of three and a maximum of four years or longer.

But the Department of Energy and Climate Change remained bullish. “The UK is confident that the state aid case for Hinkley Point C is legally robust and we vigorously support the European Commission’s defence of its decision last year”, a  spokesman told the Guardian.

“This brings us one step closer to seeing new nuclear as part of our future low carbon energy mix. We have no reason to believe that Austria, or any other party, is preparing a case which has any merit.”

But DECC did not respond to questions about the effect that a lengthy court case might have on cost over-runs or a final investment decision.

The renewables industry has bridled at what some see as double-standards in EU decisions last year denying state aid to renewable energy in Germany, while allowing it for nuclear in the UK.

“It’s puzzling why the European Commission has decided to have a set of rules for one energy source and entirely different set for another”, said European Wind Energy Association spokesman Oliver Joy.

“If we want a level playing field for all energy forms in the EU then we need common standards that allow all technologies to compete on an equal footing.”

 


 

Arthur Neslen is the Europe environment correspondent at the Guardian. He has previously worked for the BBC, the Economist, Al Jazeera, and EurActiv, where his journalism won environmental awards. He has written two books about Israeli and Palestinian identity.

This article is a synthesis of two articles by Arthur Nelsen originally published on the Guardian: ‘Austria to launch lawsuit over Hinkley Point C nuclear subsidies‘ and ‘UK nuclear ambitions dealt fatal blow by Austrian legal challenge, say Greens‘. It is published on The Ecologist by kind permission via the Guardian Environment Network.

 

 




389354

Austria: ‘we will launch Hinkley C nuclear subsidy legal challenge by April’ Updated for 2026





Austria is to launch a legal challenge against the European Union’s (EU) decision to allow billions of pounds of subsidies for Hinkley Point C, casting fresh doubt over the UK’s first planned nuclear reactors in 20 years.

In October, the EU approved the controversial £17.6bn subsidy deal for the power station, which is expected to provide 7% of the UK’s electricity by 2023.

David Cameron had previously hailed the subsidy deal between the French state-owned EDF and the UK government as “a very big day for our country”. He also described the signing of the Hinkley deal as marking the next generation of nuclear power in Britain, for its ability to meet energy demand and contribute to long-term security of supply.

But the appeal by Austria, a non-nuclear nation, will be launched by April and could delay a final investment decision by the UK government for over two years.

The Guardian understands that Luxembourg is very likely to support the case in the European Court of Justice, arguing that the UK’s loan guarantees – over a 35-year period – constitute illegal state aid. Another EU country may follow suit.

“There has been a high-level decision by our Chancellor and Vice Chancellor to challenge the EU decision on Hinkley within two months of its publication in the EU’s official journal”, said Andreas Molin, the director of Austria’s environment ministry. The journal’s publication is expected in the next fortnight.

Stefan Pehringer, a foreign policy adviser to the Austrian federal chancellory said: “The Austrian government has announced its readiness to appeal against the EC’s [European Commission] decision concerning state aid for the Hinkley Point project, as it does not consider nuclear power to be a sustainable form of technology – neither in environmental nor in economic terms.”

Can Hinkley survive the 2015 election?

Work has already begun at the Hinkley site, which the UK government said will have a capacity of 3.3GW, with the electricity it generates bought at a strike-price of £92.50 per megawatt hour, around double the market rate.

EDF had planned to sign a long-awaited funding agreement with its Chinese investment partners in March, thought to be key to settling procurement plans for the £24.5bn build, and the precursor to a final investment decision.

But the lawsuit may delay such plans, and introduce uncertainty about the UK’s attitude towards Hinkley after elections in May.

The Austrian government’s analysis suggests that European court cases of this nature typically last for one and a half years. But “as this is going to be a more complicated and fundamental case, it will last a little bit longer”, Molin said. “Two years could be a rough guess.”

He added: “If you accept the argument that Hinkley constitutes a ‘market failure’ as put forward by the Commission, you could apply it to all other means of electricity production, probably all other forms of energy conversion, and it might even apply beyond the energy sector. We think that the single energy market itself is at stake in this case.”

The Commission’s hurried and paradoxical decision

The EU’s original decision last year surprised many observers, as the then-competition commissioner Joaquín Almunia had previously expressed scepticism about Hinkley’s’ conformity with an exhaustive list of strict state aid criteria.

These govern proportionality, decarbonisation, the potential for market distortion, the definition of ‘market failures’ and, crucially, whether the public monies advance an “objective of common interest” for the bloc.

No grounds for the Commission’s volte-face have yet been published, but the Guardian has seen a draft of the EU decision from last October, suggesting that one key decider had been advised that Hinkley advanced an EU ‘common interest’ around security of supply.

A Commission investigation declared itself “unsure” whether the reactor would resolve the UK’s security of supply issues, and was unconvinced that ‘diversification’ of supplies, on its own, would justify the monies involved.

“The Commission however accepted that the decision was in line with the Euratom treaty”, the draft ruling says. The Euratom treaty obliges member states to facilitate investments in nuclear power and encourage ventures that lead to the technology’s development.

Molin said that Austria would argue that the Euratom treaty could not be used in this way in state aid cases, but there would be other lines of dispute. “We will try to prove that the commission did not consider all the things which it should have considered and that there were some procedural flaws”, he said.

Minutes from the Commission’s internal discussion of the issue show that the EC’s president at the time, José Manuel Barroso, viewed the Hinkley decision as unprecedented, and said that it “touched on a politically sensitive topic”.

No contract for the Hinkley plant was put out to tender, and the ruling sparked outrage among environmentalists in the EU, that shows no signs of dying down.

“The Commission took a political decision disguised as a legal one”, said Mark Johnston, a senior adviser to the European Policy Centre. “Barroso thought it would be easier to bend over for Cameron than to defend the single energy market. The significance of the case for energy investments across Europe could not be greater.”

A ‘fatal blow’, claim the Greens

Molly Scott Cato, the Green Party MEP for the South West region, which includes Hinkley, said: “I think that this court case is certainly going to delay the signing and also the construction of Hinkley.”

“As one of the government’s main arguments for Hinkley was that it would solve the ‘energy gap’ before renewables could be brought onstream, it is a fatal blow to Hinkley as part of a future energy strategy for the UK.”

Natalie Bennett, the leader of the Green Party, said that such claims now seemed risible. “I think we have seen the final generation of nuclear power, I am very pleased to say. It’s gone, it’s dusted. Lets focus on evidence-based renewables and energy conservation futures.”

But the UKIP MEP and energy spokesman, Roger Helmer, offered strong support for nuclear energy, qualified only by a caveat that the government’s Hinkley deal had been “excessively expensive” because of regulatory uncertainty from Brussels.

“Given that Hinkley is a trailblazer for the new generation of nuclear and now looks like being held up for a long period of time, it will be extremely damaging – not just for nuclear but across the whole spectrum of industry”, he said.

No grounds for such state aid in EU treaties

Dr Dörte Fouquet, a lawyer for the Brussels-based law firm Becker Büttner Held, which specialises in energy and competition law, said Austria’s chances of success were “pretty high” because there were no grounds for giving such state aid under EU treaty law and Austria would question the common European interest in building a nuclear power plant in the UK.

She added that long delays now appeared inevitable: “A court process that kicks off in May would take a minimum of two years and if it goes into appeals, you’d then be looking at another two years. So it could be a minimum of three and a maximum of four years or longer.

But the Department of Energy and Climate Change remained bullish. “The UK is confident that the state aid case for Hinkley Point C is legally robust and we vigorously support the European Commission’s defence of its decision last year”, a  spokesman told the Guardian.

“This brings us one step closer to seeing new nuclear as part of our future low carbon energy mix. We have no reason to believe that Austria, or any other party, is preparing a case which has any merit.”

But DECC did not respond to questions about the effect that a lengthy court case might have on cost over-runs or a final investment decision.

The renewables industry has bridled at what some see as double-standards in EU decisions last year denying state aid to renewable energy in Germany, while allowing it for nuclear in the UK.

“It’s puzzling why the European Commission has decided to have a set of rules for one energy source and entirely different set for another”, said European Wind Energy Association spokesman Oliver Joy.

“If we want a level playing field for all energy forms in the EU then we need common standards that allow all technologies to compete on an equal footing.”

 


 

Arthur Neslen is the Europe environment correspondent at the Guardian. He has previously worked for the BBC, the Economist, Al Jazeera, and EurActiv, where his journalism won environmental awards. He has written two books about Israeli and Palestinian identity.

This article is a synthesis of two articles by Arthur Nelsen originally published on the Guardian: ‘Austria to launch lawsuit over Hinkley Point C nuclear subsidies‘ and ‘UK nuclear ambitions dealt fatal blow by Austrian legal challenge, say Greens‘. It is published on The Ecologist by kind permission via the Guardian Environment Network.

 

 




389354

Austria: ‘we will launch Hinkley C nuclear subsidy legal challenge by April’ Updated for 2026





Austria is to launch a legal challenge against the European Union’s (EU) decision to allow billions of pounds of subsidies for Hinkley Point C, casting fresh doubt over the UK’s first planned nuclear reactors in 20 years.

In October, the EU approved the controversial £17.6bn subsidy deal for the power station, which is expected to provide 7% of the UK’s electricity by 2023.

David Cameron had previously hailed the subsidy deal between the French state-owned EDF and the UK government as “a very big day for our country”. He also described the signing of the Hinkley deal as marking the next generation of nuclear power in Britain, for its ability to meet energy demand and contribute to long-term security of supply.

But the appeal by Austria, a non-nuclear nation, will be launched by April and could delay a final investment decision by the UK government for over two years.

The Guardian understands that Luxembourg is very likely to support the case in the European Court of Justice, arguing that the UK’s loan guarantees – over a 35-year period – constitute illegal state aid. Another EU country may follow suit.

“There has been a high-level decision by our Chancellor and Vice Chancellor to challenge the EU decision on Hinkley within two months of its publication in the EU’s official journal”, said Andreas Molin, the director of Austria’s environment ministry. The journal’s publication is expected in the next fortnight.

Stefan Pehringer, a foreign policy adviser to the Austrian federal chancellory said: “The Austrian government has announced its readiness to appeal against the EC’s [European Commission] decision concerning state aid for the Hinkley Point project, as it does not consider nuclear power to be a sustainable form of technology – neither in environmental nor in economic terms.”

Can Hinkley survive the 2015 election?

Work has already begun at the Hinkley site, which the UK government said will have a capacity of 3.3GW, with the electricity it generates bought at a strike-price of £92.50 per megawatt hour, around double the market rate.

EDF had planned to sign a long-awaited funding agreement with its Chinese investment partners in March, thought to be key to settling procurement plans for the £24.5bn build, and the precursor to a final investment decision.

But the lawsuit may delay such plans, and introduce uncertainty about the UK’s attitude towards Hinkley after elections in May.

The Austrian government’s analysis suggests that European court cases of this nature typically last for one and a half years. But “as this is going to be a more complicated and fundamental case, it will last a little bit longer”, Molin said. “Two years could be a rough guess.”

He added: “If you accept the argument that Hinkley constitutes a ‘market failure’ as put forward by the Commission, you could apply it to all other means of electricity production, probably all other forms of energy conversion, and it might even apply beyond the energy sector. We think that the single energy market itself is at stake in this case.”

The Commission’s hurried and paradoxical decision

The EU’s original decision last year surprised many observers, as the then-competition commissioner Joaquín Almunia had previously expressed scepticism about Hinkley’s’ conformity with an exhaustive list of strict state aid criteria.

These govern proportionality, decarbonisation, the potential for market distortion, the definition of ‘market failures’ and, crucially, whether the public monies advance an “objective of common interest” for the bloc.

No grounds for the Commission’s volte-face have yet been published, but the Guardian has seen a draft of the EU decision from last October, suggesting that one key decider had been advised that Hinkley advanced an EU ‘common interest’ around security of supply.

A Commission investigation declared itself “unsure” whether the reactor would resolve the UK’s security of supply issues, and was unconvinced that ‘diversification’ of supplies, on its own, would justify the monies involved.

“The Commission however accepted that the decision was in line with the Euratom treaty”, the draft ruling says. The Euratom treaty obliges member states to facilitate investments in nuclear power and encourage ventures that lead to the technology’s development.

Molin said that Austria would argue that the Euratom treaty could not be used in this way in state aid cases, but there would be other lines of dispute. “We will try to prove that the commission did not consider all the things which it should have considered and that there were some procedural flaws”, he said.

Minutes from the Commission’s internal discussion of the issue show that the EC’s president at the time, José Manuel Barroso, viewed the Hinkley decision as unprecedented, and said that it “touched on a politically sensitive topic”.

No contract for the Hinkley plant was put out to tender, and the ruling sparked outrage among environmentalists in the EU, that shows no signs of dying down.

“The Commission took a political decision disguised as a legal one”, said Mark Johnston, a senior adviser to the European Policy Centre. “Barroso thought it would be easier to bend over for Cameron than to defend the single energy market. The significance of the case for energy investments across Europe could not be greater.”

A ‘fatal blow’, claim the Greens

Molly Scott Cato, the Green Party MEP for the South West region, which includes Hinkley, said: “I think that this court case is certainly going to delay the signing and also the construction of Hinkley.”

“As one of the government’s main arguments for Hinkley was that it would solve the ‘energy gap’ before renewables could be brought onstream, it is a fatal blow to Hinkley as part of a future energy strategy for the UK.”

Natalie Bennett, the leader of the Green Party, said that such claims now seemed risible. “I think we have seen the final generation of nuclear power, I am very pleased to say. It’s gone, it’s dusted. Lets focus on evidence-based renewables and energy conservation futures.”

But the UKIP MEP and energy spokesman, Roger Helmer, offered strong support for nuclear energy, qualified only by a caveat that the government’s Hinkley deal had been “excessively expensive” because of regulatory uncertainty from Brussels.

“Given that Hinkley is a trailblazer for the new generation of nuclear and now looks like being held up for a long period of time, it will be extremely damaging – not just for nuclear but across the whole spectrum of industry”, he said.

No grounds for such state aid in EU treaties

Dr Dörte Fouquet, a lawyer for the Brussels-based law firm Becker Büttner Held, which specialises in energy and competition law, said Austria’s chances of success were “pretty high” because there were no grounds for giving such state aid under EU treaty law and Austria would question the common European interest in building a nuclear power plant in the UK.

She added that long delays now appeared inevitable: “A court process that kicks off in May would take a minimum of two years and if it goes into appeals, you’d then be looking at another two years. So it could be a minimum of three and a maximum of four years or longer.

But the Department of Energy and Climate Change remained bullish. “The UK is confident that the state aid case for Hinkley Point C is legally robust and we vigorously support the European Commission’s defence of its decision last year”, a  spokesman told the Guardian.

“This brings us one step closer to seeing new nuclear as part of our future low carbon energy mix. We have no reason to believe that Austria, or any other party, is preparing a case which has any merit.”

But DECC did not respond to questions about the effect that a lengthy court case might have on cost over-runs or a final investment decision.

The renewables industry has bridled at what some see as double-standards in EU decisions last year denying state aid to renewable energy in Germany, while allowing it for nuclear in the UK.

“It’s puzzling why the European Commission has decided to have a set of rules for one energy source and entirely different set for another”, said European Wind Energy Association spokesman Oliver Joy.

“If we want a level playing field for all energy forms in the EU then we need common standards that allow all technologies to compete on an equal footing.”

 


 

Arthur Neslen is the Europe environment correspondent at the Guardian. He has previously worked for the BBC, the Economist, Al Jazeera, and EurActiv, where his journalism won environmental awards. He has written two books about Israeli and Palestinian identity.

This article is a synthesis of two articles by Arthur Nelsen originally published on the Guardian: ‘Austria to launch lawsuit over Hinkley Point C nuclear subsidies‘ and ‘UK nuclear ambitions dealt fatal blow by Austrian legal challenge, say Greens‘. It is published on The Ecologist by kind permission via the Guardian Environment Network.

 

 




389354

Austria: ‘we will launch Hinkley C nuclear subsidy legal challenge by April’ Updated for 2026





Austria is to launch a legal challenge against the European Union’s (EU) decision to allow billions of pounds of subsidies for Hinkley Point C, casting fresh doubt over the UK’s first planned nuclear reactors in 20 years.

In October, the EU approved the controversial £17.6bn subsidy deal for the power station, which is expected to provide 7% of the UK’s electricity by 2023.

David Cameron had previously hailed the subsidy deal between the French state-owned EDF and the UK government as “a very big day for our country”. He also described the signing of the Hinkley deal as marking the next generation of nuclear power in Britain, for its ability to meet energy demand and contribute to long-term security of supply.

But the appeal by Austria, a non-nuclear nation, will be launched by April and could delay a final investment decision by the UK government for over two years.

The Guardian understands that Luxembourg is very likely to support the case in the European Court of Justice, arguing that the UK’s loan guarantees – over a 35-year period – constitute illegal state aid. Another EU country may follow suit.

“There has been a high-level decision by our Chancellor and Vice Chancellor to challenge the EU decision on Hinkley within two months of its publication in the EU’s official journal”, said Andreas Molin, the director of Austria’s environment ministry. The journal’s publication is expected in the next fortnight.

Stefan Pehringer, a foreign policy adviser to the Austrian federal chancellory said: “The Austrian government has announced its readiness to appeal against the EC’s [European Commission] decision concerning state aid for the Hinkley Point project, as it does not consider nuclear power to be a sustainable form of technology – neither in environmental nor in economic terms.”

Can Hinkley survive the 2015 election?

Work has already begun at the Hinkley site, which the UK government said will have a capacity of 3.3GW, with the electricity it generates bought at a strike-price of £92.50 per megawatt hour, around double the market rate.

EDF had planned to sign a long-awaited funding agreement with its Chinese investment partners in March, thought to be key to settling procurement plans for the £24.5bn build, and the precursor to a final investment decision.

But the lawsuit may delay such plans, and introduce uncertainty about the UK’s attitude towards Hinkley after elections in May.

The Austrian government’s analysis suggests that European court cases of this nature typically last for one and a half years. But “as this is going to be a more complicated and fundamental case, it will last a little bit longer”, Molin said. “Two years could be a rough guess.”

He added: “If you accept the argument that Hinkley constitutes a ‘market failure’ as put forward by the Commission, you could apply it to all other means of electricity production, probably all other forms of energy conversion, and it might even apply beyond the energy sector. We think that the single energy market itself is at stake in this case.”

The Commission’s hurried and paradoxical decision

The EU’s original decision last year surprised many observers, as the then-competition commissioner Joaquín Almunia had previously expressed scepticism about Hinkley’s’ conformity with an exhaustive list of strict state aid criteria.

These govern proportionality, decarbonisation, the potential for market distortion, the definition of ‘market failures’ and, crucially, whether the public monies advance an “objective of common interest” for the bloc.

No grounds for the Commission’s volte-face have yet been published, but the Guardian has seen a draft of the EU decision from last October, suggesting that one key decider had been advised that Hinkley advanced an EU ‘common interest’ around security of supply.

A Commission investigation declared itself “unsure” whether the reactor would resolve the UK’s security of supply issues, and was unconvinced that ‘diversification’ of supplies, on its own, would justify the monies involved.

“The Commission however accepted that the decision was in line with the Euratom treaty”, the draft ruling says. The Euratom treaty obliges member states to facilitate investments in nuclear power and encourage ventures that lead to the technology’s development.

Molin said that Austria would argue that the Euratom treaty could not be used in this way in state aid cases, but there would be other lines of dispute. “We will try to prove that the commission did not consider all the things which it should have considered and that there were some procedural flaws”, he said.

Minutes from the Commission’s internal discussion of the issue show that the EC’s president at the time, José Manuel Barroso, viewed the Hinkley decision as unprecedented, and said that it “touched on a politically sensitive topic”.

No contract for the Hinkley plant was put out to tender, and the ruling sparked outrage among environmentalists in the EU, that shows no signs of dying down.

“The Commission took a political decision disguised as a legal one”, said Mark Johnston, a senior adviser to the European Policy Centre. “Barroso thought it would be easier to bend over for Cameron than to defend the single energy market. The significance of the case for energy investments across Europe could not be greater.”

A ‘fatal blow’, claim the Greens

Molly Scott Cato, the Green Party MEP for the South West region, which includes Hinkley, said: “I think that this court case is certainly going to delay the signing and also the construction of Hinkley.”

“As one of the government’s main arguments for Hinkley was that it would solve the ‘energy gap’ before renewables could be brought onstream, it is a fatal blow to Hinkley as part of a future energy strategy for the UK.”

Natalie Bennett, the leader of the Green Party, said that such claims now seemed risible. “I think we have seen the final generation of nuclear power, I am very pleased to say. It’s gone, it’s dusted. Lets focus on evidence-based renewables and energy conservation futures.”

But the UKIP MEP and energy spokesman, Roger Helmer, offered strong support for nuclear energy, qualified only by a caveat that the government’s Hinkley deal had been “excessively expensive” because of regulatory uncertainty from Brussels.

“Given that Hinkley is a trailblazer for the new generation of nuclear and now looks like being held up for a long period of time, it will be extremely damaging – not just for nuclear but across the whole spectrum of industry”, he said.

No grounds for such state aid in EU treaties

Dr Dörte Fouquet, a lawyer for the Brussels-based law firm Becker Büttner Held, which specialises in energy and competition law, said Austria’s chances of success were “pretty high” because there were no grounds for giving such state aid under EU treaty law and Austria would question the common European interest in building a nuclear power plant in the UK.

She added that long delays now appeared inevitable: “A court process that kicks off in May would take a minimum of two years and if it goes into appeals, you’d then be looking at another two years. So it could be a minimum of three and a maximum of four years or longer.

But the Department of Energy and Climate Change remained bullish. “The UK is confident that the state aid case for Hinkley Point C is legally robust and we vigorously support the European Commission’s defence of its decision last year”, a  spokesman told the Guardian.

“This brings us one step closer to seeing new nuclear as part of our future low carbon energy mix. We have no reason to believe that Austria, or any other party, is preparing a case which has any merit.”

But DECC did not respond to questions about the effect that a lengthy court case might have on cost over-runs or a final investment decision.

The renewables industry has bridled at what some see as double-standards in EU decisions last year denying state aid to renewable energy in Germany, while allowing it for nuclear in the UK.

“It’s puzzling why the European Commission has decided to have a set of rules for one energy source and entirely different set for another”, said European Wind Energy Association spokesman Oliver Joy.

“If we want a level playing field for all energy forms in the EU then we need common standards that allow all technologies to compete on an equal footing.”

 


 

Arthur Neslen is the Europe environment correspondent at the Guardian. He has previously worked for the BBC, the Economist, Al Jazeera, and EurActiv, where his journalism won environmental awards. He has written two books about Israeli and Palestinian identity.

This article is a synthesis of two articles by Arthur Nelsen originally published on the Guardian: ‘Austria to launch lawsuit over Hinkley Point C nuclear subsidies‘ and ‘UK nuclear ambitions dealt fatal blow by Austrian legal challenge, say Greens‘. It is published on The Ecologist by kind permission via the Guardian Environment Network.

 

 




389354

Austria: ‘we will launch Hinkley C nuclear subsidy legal challenge by April’ Updated for 2026





Austria is to launch a legal challenge against the European Union’s (EU) decision to allow billions of pounds of subsidies for Hinkley Point C, casting fresh doubt over the UK’s first planned nuclear reactors in 20 years.

In October, the EU approved the controversial £17.6bn subsidy deal for the power station, which is expected to provide 7% of the UK’s electricity by 2023.

David Cameron had previously hailed the subsidy deal between the French state-owned EDF and the UK government as “a very big day for our country”. He also described the signing of the Hinkley deal as marking the next generation of nuclear power in Britain, for its ability to meet energy demand and contribute to long-term security of supply.

But the appeal by Austria, a non-nuclear nation, will be launched by April and could delay a final investment decision by the UK government for over two years.

The Guardian understands that Luxembourg is very likely to support the case in the European Court of Justice, arguing that the UK’s loan guarantees – over a 35-year period – constitute illegal state aid. Another EU country may follow suit.

“There has been a high-level decision by our Chancellor and Vice Chancellor to challenge the EU decision on Hinkley within two months of its publication in the EU’s official journal”, said Andreas Molin, the director of Austria’s environment ministry. The journal’s publication is expected in the next fortnight.

Stefan Pehringer, a foreign policy adviser to the Austrian federal chancellory said: “The Austrian government has announced its readiness to appeal against the EC’s [European Commission] decision concerning state aid for the Hinkley Point project, as it does not consider nuclear power to be a sustainable form of technology – neither in environmental nor in economic terms.”

Can Hinkley survive the 2015 election?

Work has already begun at the Hinkley site, which the UK government said will have a capacity of 3.3GW, with the electricity it generates bought at a strike-price of £92.50 per megawatt hour, around double the market rate.

EDF had planned to sign a long-awaited funding agreement with its Chinese investment partners in March, thought to be key to settling procurement plans for the £24.5bn build, and the precursor to a final investment decision.

But the lawsuit may delay such plans, and introduce uncertainty about the UK’s attitude towards Hinkley after elections in May.

The Austrian government’s analysis suggests that European court cases of this nature typically last for one and a half years. But “as this is going to be a more complicated and fundamental case, it will last a little bit longer”, Molin said. “Two years could be a rough guess.”

He added: “If you accept the argument that Hinkley constitutes a ‘market failure’ as put forward by the Commission, you could apply it to all other means of electricity production, probably all other forms of energy conversion, and it might even apply beyond the energy sector. We think that the single energy market itself is at stake in this case.”

The Commission’s hurried and paradoxical decision

The EU’s original decision last year surprised many observers, as the then-competition commissioner Joaquín Almunia had previously expressed scepticism about Hinkley’s’ conformity with an exhaustive list of strict state aid criteria.

These govern proportionality, decarbonisation, the potential for market distortion, the definition of ‘market failures’ and, crucially, whether the public monies advance an “objective of common interest” for the bloc.

No grounds for the Commission’s volte-face have yet been published, but the Guardian has seen a draft of the EU decision from last October, suggesting that one key decider had been advised that Hinkley advanced an EU ‘common interest’ around security of supply.

A Commission investigation declared itself “unsure” whether the reactor would resolve the UK’s security of supply issues, and was unconvinced that ‘diversification’ of supplies, on its own, would justify the monies involved.

“The Commission however accepted that the decision was in line with the Euratom treaty”, the draft ruling says. The Euratom treaty obliges member states to facilitate investments in nuclear power and encourage ventures that lead to the technology’s development.

Molin said that Austria would argue that the Euratom treaty could not be used in this way in state aid cases, but there would be other lines of dispute. “We will try to prove that the commission did not consider all the things which it should have considered and that there were some procedural flaws”, he said.

Minutes from the Commission’s internal discussion of the issue show that the EC’s president at the time, José Manuel Barroso, viewed the Hinkley decision as unprecedented, and said that it “touched on a politically sensitive topic”.

No contract for the Hinkley plant was put out to tender, and the ruling sparked outrage among environmentalists in the EU, that shows no signs of dying down.

“The Commission took a political decision disguised as a legal one”, said Mark Johnston, a senior adviser to the European Policy Centre. “Barroso thought it would be easier to bend over for Cameron than to defend the single energy market. The significance of the case for energy investments across Europe could not be greater.”

A ‘fatal blow’, claim the Greens

Molly Scott Cato, the Green Party MEP for the South West region, which includes Hinkley, said: “I think that this court case is certainly going to delay the signing and also the construction of Hinkley.”

“As one of the government’s main arguments for Hinkley was that it would solve the ‘energy gap’ before renewables could be brought onstream, it is a fatal blow to Hinkley as part of a future energy strategy for the UK.”

Natalie Bennett, the leader of the Green Party, said that such claims now seemed risible. “I think we have seen the final generation of nuclear power, I am very pleased to say. It’s gone, it’s dusted. Lets focus on evidence-based renewables and energy conservation futures.”

But the UKIP MEP and energy spokesman, Roger Helmer, offered strong support for nuclear energy, qualified only by a caveat that the government’s Hinkley deal had been “excessively expensive” because of regulatory uncertainty from Brussels.

“Given that Hinkley is a trailblazer for the new generation of nuclear and now looks like being held up for a long period of time, it will be extremely damaging – not just for nuclear but across the whole spectrum of industry”, he said.

No grounds for such state aid in EU treaties

Dr Dörte Fouquet, a lawyer for the Brussels-based law firm Becker Büttner Held, which specialises in energy and competition law, said Austria’s chances of success were “pretty high” because there were no grounds for giving such state aid under EU treaty law and Austria would question the common European interest in building a nuclear power plant in the UK.

She added that long delays now appeared inevitable: “A court process that kicks off in May would take a minimum of two years and if it goes into appeals, you’d then be looking at another two years. So it could be a minimum of three and a maximum of four years or longer.

But the Department of Energy and Climate Change remained bullish. “The UK is confident that the state aid case for Hinkley Point C is legally robust and we vigorously support the European Commission’s defence of its decision last year”, a  spokesman told the Guardian.

“This brings us one step closer to seeing new nuclear as part of our future low carbon energy mix. We have no reason to believe that Austria, or any other party, is preparing a case which has any merit.”

But DECC did not respond to questions about the effect that a lengthy court case might have on cost over-runs or a final investment decision.

The renewables industry has bridled at what some see as double-standards in EU decisions last year denying state aid to renewable energy in Germany, while allowing it for nuclear in the UK.

“It’s puzzling why the European Commission has decided to have a set of rules for one energy source and entirely different set for another”, said European Wind Energy Association spokesman Oliver Joy.

“If we want a level playing field for all energy forms in the EU then we need common standards that allow all technologies to compete on an equal footing.”

 


 

Arthur Neslen is the Europe environment correspondent at the Guardian. He has previously worked for the BBC, the Economist, Al Jazeera, and EurActiv, where his journalism won environmental awards. He has written two books about Israeli and Palestinian identity.

This article is a synthesis of two articles by Arthur Nelsen originally published on the Guardian: ‘Austria to launch lawsuit over Hinkley Point C nuclear subsidies‘ and ‘UK nuclear ambitions dealt fatal blow by Austrian legal challenge, say Greens‘. It is published on The Ecologist by kind permission via the Guardian Environment Network.

 

 




389354